DO NOT GO TO POSTED COORDINATES. You are building a new single story house with a basement. How would you do that? There's more to building an entire house than what is listed. But what is in the list below must be done in a certain order. Example: You must set your roof trusses before you can lay your roof shingles.
0 FRAME INTERIOR WALLS
9 INSTALL SIDING
1 INSTALL WINDOWS
3 SET FOUNDATION FORMS
4 EXCAVATE
6 EXTERIOR WALL SHEATHING
space LAY SUBFLOOR
space POUR CONCRETE FOOTINGS
point BACKFILL FOUNDATION WALLS
9 POUR LOWER LEVEL CONCRETE FLOOR
2 INSTALL FLOOR JOISTS
N MOBILIZE CREW TO THE JOBSITE
W FRAME EXTERIOR WALLS
point INSTALL SHINGLES
9 DOUBLE TOP PLATES
3 SET FOOTING FORMS
4 LAY ROOF SHEATHING
3 INSTALL EXTERIOR DOORS
0 LAY ROOF TAR PAPER
space SET ROOF TRUSSES
0 POUR CONCRETE FOUNDATION
3 ANCHOR MUD SILL TO FOUNDATION WALL